Sistema Salida (Concete Plant)

 

Location

Sistema Hidraulico
Portal Salida
Quibor, Estada Lara, Venezuela

SIZE / CAPACITY
60 m3/hr

SERVICES PROVIDED

  • Conceptual Design
  • Struct./Mech. Engineering
  • Design & Supply Of Control System
  • Supply/Fabrication of all Equipment
  • Supervision of Equipment Installation
  • Commissioning and Training

SUPPLIED EQUIPMENT

  • Aggregate Loadout Hopper
  • Three Belt Conveyors
  • Aggregate 3 Position Flop Chute
  • Aggregate Storage Bins
  • Three Cement Silos
  • Three Screw Conveyors
  • Cement Weigh Hopper
  • Water Weigh Hopper
  • Pan Mixer
  • Concrete Holding Hopper
  • Dust Collection System
  • Pallet Lift System
  • Equipment Support Structure
  • Control Room/MCC/PLC System
  • Pneumatic Control System

This project, as described previously in the Yacambu project, involves the same 24 km irrigation tunnel, in Los Andes spurs. As with the plant at Portal de Entrada, in the Yacambu valley, Team Mixing Technologies was contracted to design, supply, and commission a concrete batch plant at the Portal Salida featuring a Voeller pan mixer. This plant is also PLC controlled and included an Motor Control Center as part of the automated package.

The project itself involves tunneling from the outlet of the tunnel in the Quibor valley, towards Yacambu. The tunnel, when completed, will be turned over to the Environmental and Natural Resources Ministry of Venezuela.